Regulation 7(2): Combustible Materials in External Walls

Sources: Building Regulations 2010 regulation 7 (England, as amended), with Approved Document B (2019 edition incorporating 2020, 2022, 2025 and 2026 amendments) and Approved Document 7 (2013 edition incorporating 2018 amendments)

Check your set instantly
Quick answer

Regulation 7(2) bans combustible materials in the external walls of relevant buildings. A relevant building has a storey at least 18 m above ground and contains dwellings, an institution or a room for residential purposes. Materials must be class A2-s1, d0 or A1, apart from those regulation 7(3) exempts. Regulation 7(1A) bans relevant metal composite material at any height.

The Pirros Quality Management System can check the reaction-to-fire class of every layer in your external wall build-ups in your set and Revit model, instantly.

The manual way

How to check the code requirements

Regulation 7(2) turns on two facts the drawings show: the top storey's height and the building's use. Check those first, then every layer of the wall and every attachment.

  • Measure the storeys. Dimension each storey's floor surface above the lowest ground level adjoining the building (7(4)(b)). Leave out roof-top plant areas and plant-room-only storeys.
  • Confirm the use. Dwellings, an institution or a room for residential purposes make it a relevant building. Rooms in hotels, hostels and boarding houses have counted since 1 December 2022.
  • Class every layer. List each material in the external wall build-up with its Euroclass, for example in a material schedule. Anything not exempted must be A2-s1, d0 or A1.
  • Tick off the exemptions. Check each remaining item against 7(3), such as window frames, membranes, seals, fixings and thermal breaks. Window spandrel and infill panels are not exempt.
  • Check the attachments. Balconies, solar panels and solar shading above 4.5 m are specified attachments. A balcony's top floor layer may be A1fl or A2fl-s1 over an imperforate substrate.
  • Look for metal composite panels. Relevant metal composite material is banned at any height, so check every building, not only relevant ones (7(1A)).

Regulation 7 is on legislation.gov.uk. Approved Document B explains it in Section 12 of Volume 2 and Section 10 of Volume 1, and Approved Document 7 covers regulation 7(1). The build-up is drawn on the wall section, which is where an AI-powered quality management system reads it alongside the elevations.

Elevation of a block of flats whose top storey's floor is 18 m or more above the lowest adjoining ground, making it a relevant building, with roof-top plant not counted; and a wall section in which the cladding, insulation, sheathing board, steel frame and window spandrel panel must be class A2-s1, d0 or A1, while the window and glass, membrane, fixings, thermal breaks and fire-stopping are exempt under regulation 7(3); a balcony's top floor layer is A1fl or A2fl-s1 on an imperforate substrate, and relevant metal composite panels are banned at any height under 7(1A)
Pirros Quality Management

How Pirros checks the set

The Pirros Quality Management System reviews projects against code requirements, firm standards, and project specifications, then assigns, tracks, and resolves issues before they become RFIs or rework.

  • Reads every sheet in your set against the codes you pick for the project: the Building Regulations and Approved Documents.
  • Every finding names the sheet, the location and the section behind it.
  • Findings are surfaced, never auto-applied. Your reviewer confirms, dismisses or escalates.

Requirements at a glance

Regulation 7(2): Combustible Materials in External Walls, by section
ElementRequirementSection
Regulation 7(2)Materials that become part of an external wall, or specified attachment, of a relevant building are European Classification A2-s1, d0 or A1. They are classified to BS EN 13501-1:2018.Regulation 7(2), 2(6)(b)
Relevant buildingA building with a storey at least 18 m above ground level, containing dwellings, an institution or a room for residential purposes. Roof-top plant areas and plant-room-only storeys do not count.Regulation 7(4)(a)
Which buildingsApproved Document B lists student accommodation, care homes, sheltered housing, hospitals, boarding school dormitories, hotels, hostels and boarding houses.AD B Vol 2 para 12.15 · Vol 1 para 10.14
Measuring the 18 mFrom the lowest ground level adjoining the outside of the building to the top of the floor surface of the storey.Regulation 7(4)(b)
External wallIncludes anything within a space forming part of the wall, external finishes, and windows and doors. Also any roof part pitched over 70° that adjoins a space people can enter, other than for maintenance.Regulation 2(6)(a)
Specified attachmentsBalconies and solar panels attached to an external wall, and solar shading devices more than 4.5 m above ground.Regulation 2(6)(d)
ExemptionsCavity trays between two leaves of masonry; roof parts connected to the wall; door frames and doors; electrical installations; fibre optic cables. Insulation and waterproofing below ground or up to 300 mm above it.Regulation 7(3)(a) to (e)
More exemptionsIntumescent and fire-stopping materials needed for Part B; membranes; seals, gaskets, fixings, sealants and backer rods. Solar shading parts other than the curtain or slats; thermal breaks needed for Part L; window frames and glass.Regulation 7(3)(f) to (j)
Balcony floorsThe top horizontal floor layer of a balcony may be class A1fl or A2fl-s1, with an imperforate substrate under the whole layer.Regulation 7(3)(k)
Still caughtWindow spandrel and infill panels, and solar shading curtains and slats, must comply. Membranes above ground are class B-s3, d0 at least. Thermal breaks stay small and never span two compartments.AD B Vol 2 paras 12.19, 12.22 · Vol 1 paras 10.18, 10.21
Metal composite materialNone in the external wall or specified attachments of any building, at any height. That covers panels or sheets up to 10 mm thick with two or more metal layers and a substantial layer above 35 MJ/kg.Regulation 7(1A), 2(6)(c)
Change of useWhere a building becomes a relevant building, its external walls and specified attachments may hold only A2-s1, d0 or A1 materials. The 7(3) items stay exempt.Regulations 5(k), 6(3) · AD B Vol 2 para 12.18
Below the 18 m triggerTable 12.1 sets the external surface class by use and height. In residential buildings with a storey 11 m or more, insulation and filler are class A2-s1, d0 or better.AD B Vol 2 Table 12.1, para 12.7
Regulation 7(1)All building work uses adequate and proper materials: appropriate for the circumstances, adequately mixed or prepared, and fixed to perform as designed. The work is done in a workmanlike manner.Regulation 7(1) · Approved Document 7
When it changedRegulation 7(2) came into force on 21 December 2018. SI 2022/603 added 7(1A) and brought rooms in hotels, hostels and boarding houses into scope from 1 December 2022.SI 2018/1230 · SI 2022/603

These references are to regulation 7 of the Building Regulations 2010 as it applies in England, last amended for 7(3)(k) from 5 June 2023. Regulation 7(2) took effect on 21 December 2018 and was restated by SI 2022/603 from 1 December 2022. Work notified before that date, and started by then or within six months, stays on the earlier text. Wales has its own version of regulation 7, and Scotland its own building standards.

FAQ

Frequently asked questions.

Can't find what you're looking for?
Get in touch.

The materials and workmanship regulation of the Building Regulations 2010. Regulation 7(1) requires adequate and proper materials and workmanlike work in all building work. Regulation 7(2) bans combustible materials in the external walls of relevant buildings, and 7(1A) bans relevant metal composite material on any building.

Buildings with a storey at least 18 m above ground that contain one or more dwellings, an institution or a room for residential purposes (7(4)). Approved Document B lists student accommodation, care homes, sheltered housing, hospitals, boarding school dormitories, hotels, hostels and boarding houses.

From the lowest ground level adjoining the outside of the building to the top of the storey's floor surface (regulation 7(4)(b)). Roof-top plant areas and storeys made up only of plant rooms do not count.

Cavity trays between masonry leaves, connected roof parts, doors and door frames, electrical installations, fibre optic cables, and insulation up to 300 mm above ground. Also intumescent and fire-stopping materials, membranes, seals and fixings, thermal breaks, window frames and glass, and some balcony floor layers.

Yes, where a storey is at least 18 m above ground. Rooms in hotels, hostels and boarding houses have counted since 1 December 2022, when SI 2022/603 removed their exclusion. Approved Document B lists student accommodation among relevant buildings.

Yes. Since 1 December 2022, regulation 7(1A) bans relevant metal composite material in the external walls and specified attachments of any building, at any height. It covers panels up to 10 mm thick with two or more metal layers and a substantial layer above 35 MJ/kg.

A design aid, not legal advice. Confirm requirements with Building Control.

Contains public sector information licensed under the Open Government Licence v3.0.

Talk to a product specialist about Pirros.

Set up a time with our team and see Pirros for yourself.

By submitting, you agree to our Privacy Policy and Terms of Service.